We hereby wish to inform you that the Contractor (Martin & East) has commenced with the installation of the 200 diameter water main and it has been necessary to close the parking bays in Muizenberg Main Road in the section from Atlantic Intersection to York Road to allow this work to be undertaken.  It is anticipated that these parking bays will be temporarily unavailable for two weeks.

 

Furthermore, the Contractor is also in the process of surfacing the “by-pass” along Main Road from the SAPS museum up to Bellevue building to works to commence on the 700mm repair where a leak has been detected.

 

Please be reminded that Main Road will remain open to two-way traffic until the 2 February 2015 where after the temporary 4-way and stop-go will be in place until the completion of the northern section of Phase 3, anticipated to be in May 2015.

 

Kim Diedericks

Chand Environmental Consultants